Release of New Services / Additional Loads from Existing Network in APSPDCL October-2022 To December-2022
# Section Number of Services Released EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Services Released(%) EN
1 MADANAPALLI EAST 125 0.91 25.82 3.41 100.00
2 MADANAPALLI NORTH 106 0.98 25.23 3.63 100.00
3 MADANAPALLI TOWN 317 0.92 26.6 3.21 100.00
4 MADANAPALLI WEST 133 0.91 8.05 3.37 100.00
5 RAMA SAMUDRAM 69 1.74 19.65 5.7 100.00
Total 750 0.91 26.6 3.56 100.00