Release of New Services / Additional Loads from Existing Network in APSPDCL October-2022 To December-2022
# Sub-Division Number of Services Released EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Services Released(%) EN
1 MADANAPALLI OPERATION 750 0.91 26.6 3.56 100.00
2 MULAKALACHERVU 285 0.76 13.98 4.13 100.00
3 RURAL-MADANAPALLI 314 0.92 26.91 4.32 100.00
Total 1349 0.76 26.91 3.86 100.00