Release of New Services / Additional Loads from Existing Network in APSPDCL April-2022 To June-2022
# Section Number of Services Released EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Services Released(%) EN
1 CHEJERLA 61 1.87 10.87 5.47 100.00
2 KALUVOYA 55 1.54 5.7 2.26 100.00
3 PODALAKUR 100 1.37 23.79 4.47 100.00
4 VIRUVUR 18 1.37 10.83 3.8 100.00
Total 234 1.37 23.79 4.16 100.00