Release of New Services / Additional Loads from Existing Network in APSPDCL July-2022 To September-2022
# Section Number of Services Released EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Services Released(%) EN
1 LINGALA 37 0.22 6.73 3.22 100.00
2 PULIVENDULA(RURALS) 41 0.54 4.54 2.58 100.00
3 PULIVENDULA(TOWN) 242 0.07 2.76 0.88 100.00
Total 320 0.07 6.73 1.37 100.00