Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Circle Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ANANTHAPUR 329 0.68 90.02 7.73 81.76
2 KADAPA 234 0.08 44.02 6.64 80.34
3 KURNOOL 327 3.01 81.0 7.7 69.42
4 NELLORE 425 3.01 32.93 6.64 85.41
5 TIRUPATI 535 0.25 47.95 6.66 85.79
Total 1850 0.08 90.02 7.03 81.41