Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL April-2022 To June-2022
# Circle Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ANANTHAPUR 1056 0.45 55.85 9.35 74.62
2 KADAPA 906 0.5 24.74 6.3 80.79
3 KURNOOL 986 0.75 17.98 5.96 87.02
4 NELLORE 1576 0.66 19.79 6.36 85.03
5 TIRUPATI 2174 0.83 39.9 6.66 92.55
Total 6698 0.45 55.85 6.86 85.55