Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHITTOOR RURALS 13 3.45 13.0 9.17 23.08
2 CHITTOOR TOWN 58 0.31 44.0 6.85 93.10
3 MADANAPALE 70 3.01 22.0 6.87 81.43
4 PILERU 10 5.0 20.96 8.53 50.00
5 PUNGANUR 20 0.25 6.79 5.13 100.00
6 PUTTUR 54 3.36 23.0 8.46 62.96
7 TIRUPATI RURALS 96 3.01 47.95 6.62 94.79
8 TIRUPATI TOWN 214 3.01 27.0 6.01 91.12
Total 535 0.25 47.95 6.66 85.79