Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 OPN SUBSTATION-TPT 10 4.88 6.64 6.18 100.00
2 TIRUCHANUR CCO 56 3.01 6.71 5.45 100.00
3 TIRUPATI RURALS II 3 6.71 11.0 8.9 33.33
4 TIRUPATI SOUTH 33 3.45 6.79 5.36 100.00
Total 102 3.01 11.0 5.59 98.04