Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 RENIGUNTA 7 3.45 11.0 6.31 85.71
2 TIRUPATI CCO 102 3.01 11.0 5.59 98.04
3 TIRUPATI OPERATION1 21 3.96 6.79 5.93 100.00
4 TIRUPATI OPERATION2 84 3.01 27.0 6.51 80.95
Total 214 3.01 27.0 6.01 91.12