Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 DHAMINEDU 41 4.87 16.88 6.88 90.24
2 KORLAGUNTA 31 4.85 6.9 6.27 100.00
3 MANGALAM 24 4.87 20.9 8.47 83.33
4 MANGALAM RURALS 168 4.87 13.89 6.35 97.62
5 TIRUPATI EAST 4 4.89 6.89 5.89 100.00
Total 268 4.85 20.9 6.61 95.52