Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 RENIGUNTA 5 5.66 29.84 13.8 40.00
2 TIRUPATI CCO 75 3.01 29.03 6.65 88.00
3 TIRUPATI OPERATION1 25 3.45 13.98 5.83 96.00
4 TIRUPATI OPERATION2 57 3.36 26.46 6.6 91.23
Total 162 3.01 29.84 6.73 88.89