Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 RENIGUNTA 24 1.31 15.88 6.43 75.00
2 TIRUPATI CCO 25 3.81 12.93 7.09 64.00
3 TIRUPATI OPERATION2 17 4.1 15.62 6.98 76.47
Total 66 1.31 15.88 6.82 71.21