Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 RENIGUNTA 5 5.0 12.0 8.8 40.00
2 TIRUPATI CCO 32 3.0 7.0 5.47 100.00
3 TIRUPATI OPERATION2 63 3.0 14.0 6.21 84.13
Total 100 3.0 14.0 6.1 87.00