Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHANDRAGIRI 44 1.98 14.32 5.93 84.09
2 PAKALA 3 3.36 24.71 11.4 66.67
3 SRIKALAHASTI OPERATION 6 4.88 11.71 8.11 50.00
4 SRIKALAHASTI RURAL 2 10.03 11.99 11.01 0.00
Total 55 1.98 24.71 6.65 76.36