Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHANDRAGIRI 8 2.0 11.0 4.5 87.50
2 PAKALA 11 3.0 7.0 5.36 100.00
3 SRIKALAHASTI OPERATION 4 5.0 12.0 7.0 75.00
4 SRIKALAHASTI RURAL 3 7.0 12.0 8.67 66.67
Total 26 2.0 12.0 5.73 88.46