Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHANDRAGIRI OPERATION 43 1.88 12.88 6.54 90.70
2 CHANDRAGIRI RURAL 17 4.88 15.88 9.0 64.71
3 TIRUPATI RURAL 46 1.88 14.88 6.45 93.48
Total 106 1.88 15.88 6.89 87.74