Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NARAYANAVARAM 4 4.85 35.89 14.12 50.00
2 PUTTUR RURALS 4 1.89 14.89 7.89 50.00
3 PUTTUR URBAN 12 4.87 26.88 7.88 91.67
4 RAYALACHERUVU 6 3.88 6.88 5.71 100.00
5 VADAMALAPETA 4 6.88 20.88 13.14 25.00
Total 30 1.89 35.89 8.98 73.33