Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NAGARI OPERATION 6 3.88 17.89 9.72 50.00
2 NAGARI RURAL 8 3.88 12.89 8.26 62.50
3 NINDRA 3 5.88 14.89 9.22 66.67
4 PANNUR 1 6.88 6.88 6.88 100.00
Total 18 3.88 17.89 8.83 61.11