Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 KALIKIRI 4 5.44 20.96 10.25 50.00
2 PILER CCO 3 5.0 5.23 5.13 100.00
3 PILER RURALS 3 8.0 12.91 9.64 0.00
Total 10 5.0 20.96 8.53 50.00