Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 MADANAPALLI EAST 33 4.88 13.88 7.37 78.79
2 MADANAPALLI NORTH 35 5.87 17.89 10.71 20.00
3 MADANAPALLI TOWN 25 2.89 16.88 8.09 72.00
4 MADANAPALLI WEST 11 4.88 18.88 8.25 81.82
Total 104 2.89 18.88 8.76 57.69