Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 MADANAPALLI OPERATION 53 3.01 19.0 6.09 92.45
2 MULAKALACHERVU 7 4.88 12.0 8.52 42.86
3 RURAL-MADANAPALLI 10 3.38 22.0 9.82 50.00
Total 70 3.01 22.0 6.87 81.43