# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 MADANAPALLI OPERATION 56 3.6 15.84 8.13 58.93
2 MULAKALACHERVU 13 4.51 16.24 7.7 76.92
3 PUNGANUR CCO 37 2.0 18.69 5.59 91.89
4 RURAL-MADANAPALLI 17 2.57 9.88 5.64 82.35
Total 123 2.0 18.69 6.98 73.98