Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Jan-2021 To Mar-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 MADANAPALLI OPERATION 17 0.0 0.0 0.0 100.00
2 MULAKALACHERVU 12 0.0 0.0 0.0 100.00
3 PUNGANUR CCO 12 0.0 0.0 0.0 100.00
4 RURAL-MADANAPALLI 9 0.0 0.0 0.0 100.00
Total 50 0.0 0.0 0.0 100.00