Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 GREAMSPET WEST 2 5.72 5.8 5.76 100.00
2 KONGAREDDI PALLI 32 3.38 6.7 5.53 100.00
3 MITTOOR NORTH 2 5.79 6.23 6.01 100.00
4 SANTHAPETA SOUTH 3 5.15 6.49 5.92 100.00
Total 39 3.38 6.7 5.6 100.00