Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHITTOOR CCO 14 0.31 44.0 10.07 78.57
2 CHITTOOR OPERATION 39 3.38 6.7 5.6 100.00
3 CHITTOOR RURAL-III 5 4.85 14.0 7.55 80.00
Total 58 0.31 44.0 6.85 93.10