Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHITTOOR CCO 38 0.28 15.39 6.47 78.95
2 CHITTOOR OPERATION 17 4.4 14.34 8.28 52.94
3 CHITTOOR RURAL-III 24 3.98 15.87 7.64 70.83
Total 79 0.28 15.87 7.22 70.89