Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL January-2022 To March-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHITTOOR CCO 40 1.87 23.95 7.53 87.50
2 CHITTOOR RURAL-3 34 2.7 23.79 8.31 64.71
3 CHITTOOR TOWN 42 2.79 51.95 9.67 66.67
Total 116 1.87 51.95 8.53 73.28