Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHITTOOR CCO 1 6.0 6.0 6.0 100.00
2 CHITTOOR OPERATION 12 3.0 16.0 6.42 91.67
3 CHITTOOR RURAL-III 3 6.0 16.0 9.33 66.67
Total 16 3.0 16.0 6.94 87.50