Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 CHITTOOR RURAL-I 6 3.11 111.62 25.58 50.00
2 PAIPALLE CCO 3 4.75 5.97 5.24 100.00
3 PALAMANER 14 0.08 96.39 14.52 71.43
Total 23 0.08 111.62 16.2 69.57