Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BAIREDDIPALLE 1 5.46 5.46 5.46 100.00
2 GANGAVARAM 10 0.13 16.73 7.89 50.00
3 PALAMANER OPERATION 4 2.79 11.19 5.52 75.00
4 PALAMANER RURAL 5 4.35 5.74 5.25 100.00
5 V.KOTA 1 5.66 5.66 5.66 100.00
Total 21 0.13 16.73 6.59 71.43