Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BANGARUPALYAM 6 4.89 11.08 6.61 83.33
2 BANGARUPALYAM RURAL 7 1.63 11.06 6.11 71.43
3 YADAMARY 9 3.54 14.01 8.26 55.56
Total 22 1.63 14.01 7.13 68.18