Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2022 To September-2022
# Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ATMAKURU 7 0.94 19.89 8.89 57.14
2 GUDUR 9 0.94 11.36 4.6 77.78
3 KAVALI 134 0.65 120.38 6.57 90.30
4 NAIDUPETA 16 2.95 9.95 5.88 87.50
5 NELLORE RURALS 117 2.9 105.02 8.75 79.49
6 NELLORE TOWN 272 0.86 48.96 6.04 96.32
Total 555 0.65 120.38 6.74 90.27