Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 A.K. NAGAR 15 4.88 13.88 9.09 60.00
2 B.V.NAGAR 109 4.87 16.9 8.54 76.15
3 INDUSTRIAL ESTATE 50 4.85 6.9 6.16 100.00
Total 174 4.85 16.9 7.9 81.61