Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NELLORE TOWN III 38 2.89 16.9 7.99 78.95
2 NELLORE TOWN-I 174 4.85 16.9 7.9 81.61
3 NELLORE TOWN-II 140 4.87 18.88 7.95 73.57
Total 352 2.89 18.88 7.93 78.13