Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NELLORE TOWN I 35 4.0 17.0 10.23 45.71
2 NELLORE TOWN II 20 7.0 9.0 8.8 10.00
3 NELLORE TOWN III 7 10.0 11.0 10.71 0.00
Total 62 4.0 17.0 9.82 29.03