Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 MUTHUKURU 12 5.88 14.89 9.47 58.33
2 NELLORE RURAL-1 4 4.88 14.88 8.13 75.00
3 NELLORE RURAL-2 27 4.87 6.9 6.26 100.00
4 NELLORE RURAL-3 33 2.89 18.88 6.79 84.85
5 VENKATACHALAM C-O 5 4.88 13.88 7.29 80.00
Total 81 2.89 18.88 7.11 85.19