Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 INDUKURPET 21 4.89 16.9 8.69 71.43
2 NELLORE RURAL 81 2.89 18.88 7.11 85.19
3 PODALAKUR 9 4.88 67.9 18.66 66.67
Total 111 2.89 67.9 8.34 81.08