Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL July-2021 To September-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 INDUKURPETA C AND O 42 4.64 14.2 6.64 80.95
2 NELLORE RURALS 46 2.93 16.42 6.76 76.09
3 PODALAKUR C AND O 23 4.58 15.62 7.77 65.22
Total 111 2.93 16.42 6.92 75.68