Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NAIDUPETA 6 4.42 19.91 11.31 33.33
2 SULLURPETA 25 4.42 27.02 7.56 64.00
3 VENKATAGIRI C AND O 6 5.75 16.04 10.62 33.33
Total 37 4.42 27.02 8.66 54.05