# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 NAIDUPETA 14 4.45 11.97 6.58 78.57
2 SULLURPETA 14 4.36 15.43 7.19 71.43
3 VENKATAGIRI C AND O 6 4.83 15.15 7.43 83.33
Total 34 4.36 15.43 6.98 76.47