Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Section Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ALLURU RURALS 15 4.87 6.89 6.02 100.00
2 UTUKUR 5 4.88 35.88 16.68 20.00
3 VIDAVALUR 4 4.9 25.88 12.89 50.00
Total 17 4.88 61.88 13.65 70.59