Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BUCHI 58 0.88 43.88 9.4 72.41
2 KALIGIRI 9 4.89 51.9 15.0 44.44
3 KAVALI 17 4.88 61.88 13.65 70.59
4 KOVUR 52 4.85 6.9 6.21 100.00
5 NR PALEM 24 4.87 35.88 9.39 75.00
Total 160 0.88 61.88 9.13 80.00