Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL January-2022 To March-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BUCHI 49 3.95 20.79 7.63 75.51
2 KALIGIRI 10 3.62 35.95 13.0 20.00
3 KAVALI 39 6.7 24.7 7.61 92.31
4 KOVUR 15 1.83 26.95 14.98 40.00
5 NR PALEM 23 2.83 10.96 7.63 65.22
Total 136 1.83 35.95 8.83 70.59