Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 BUCHIREDDY PALEM 13 4.0 17.0 11.23 30.77
2 KALIGIRI 1 9.0 9.0 9.0 0.00
3 KAVALI 2 5.0 6.0 5.5 100.00
4 KOVUR 3 10.0 14.0 11.33 0.00
5 N.R.PALEM 1 5.0 5.0 5.0 100.00
Total 20 4.0 17.0 10.25 35.00