Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 GUDUR 8 4.88 55.9 18.51 62.50
2 GUDUR RURAL 19 4.89 41.86 12.35 36.84
3 KOTA 3 2.89 6.88 4.55 100.00
Total 30 2.89 55.9 13.21 50.00