Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL January-2022 To March-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 GUDUR 21 5.94 25.96 10.13 52.38
2 GUDUR RURAL 28 6.7 26.95 9.41 75.00
3 KOTA 8 3.7 27.62 10.82 50.00
Total 57 3.7 27.62 9.88 63.16