Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ATMAKURU 5 4.42 8.72 6.18 80.00
2 UDAYAGIRI 4 4.57 15.86 8.21 75.00
Total 9 4.42 15.86 7.08 77.78