Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL January-2022 To March-2022
# Sub-Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ATMAKUR 21 0.91 42.95 12.05 52.38
2 UDAYAGIRI 4 6.95 60.96 22.41 25.00
Total 25 0.91 60.96 13.71 48.00