Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL January-2022 To March-2022
# Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ADONI 219 0.95 26.96 7.16 87.67
2 DHONE 215 0.7 26.94 7.92 76.74
3 KURNOOL 448 0.91 26.95 7.77 84.15
4 KURNOOL RURALS 112 2.95 26.87 9.15 63.39
5 NANDYAL 306 0.62 72.79 7.45 87.58
Total 1300 0.62 72.79 7.73 82.54