Processing of application for New Services / Additional Loads where network expansion required -- LT in APSPDCL Apr-2021 To Jun-2021
# Division Number of Applications LT Min Duration(Days)LT Max Duration(Days)LT Average Duration(Days)LT Applications Processed(%) LT
1 ADONI 13 5.0 16.0 8.69 61.54
2 DHONE 14 4.0 16.0 11.14 28.57
3 KURNOOL 37 3.0 14.0 6.51 78.38
4 NANDYAL 28 4.0 15.0 11.75 28.57
Total 92 3.0 16.0 9.12 53.26